Takt time calculator
Enter the shift, the planned breaks and how many units the customer needs per shift; get the pace the line has to work at.
Use the time the line is planned to run, not clock time: subtract lunch, rest breaks and scheduled meetings. Leave cycle time at 0 to skip the check.
How takt time is calculated
Takt time is the net available production time divided by customer demand for the same period. It is not how fast you can work; it is how often one finished unit has to leave the line so that output matches what customers order. The calculator subtracts planned breaks from the shift, converts the result to seconds and divides by the units required.
Example: an 8-hour shift is 480 minutes. Remove a 30-minute lunch and 450 minutes, or 27,000 seconds, remain. If customers need 450 units per shift, takt time is 27,000 ÷ 450 = 60 seconds per unit, which is 60 units an hour. A bottleneck station with a 54-second cycle time can build 500 units in that time, so it has 10% headroom.
| Net time per shift | Demand | Takt time | Units per hour |
|---|---|---|---|
| 450 min | 360 units | 75 s | 48 |
| 450 min | 450 units | 60 s | 60 |
| 450 min | 540 units | 50 s | 72 |
| 420 min | 840 units | 30 s | 120 |
| 420 min | 210 units | 2 min | 30 |
Using takt time on the shop floor
Compare takt with the cycle time of every station. Any step slower than takt is a bottleneck that guarantees missed output or overtime; a step much faster than takt usually means idle operators or a pile of work in progress waiting downstream. Lean practitioners often plan to run slightly faster than takt, a figure sometimes called planned cycle time, to absorb small stoppages and changeovers.
Takt changes whenever demand changes, so recalculate it when the order book moves rather than treating it as a fixed property of the line. The most frequent mistake is using gross shift time: if you forget to remove breaks, team meetings or planned maintenance, the takt looks generous and the line falls behind every day. The opposite error is subtracting unplanned downtime; that belongs in your efficiency or OEE figures, not in takt.
The word comes from the German Takt, the beat of a conductor's baton, and the idea was refined by Toyota as part of its production system. It works best for repetitive work with steady demand. In job shops where every order differs, average takt across a product family is only a rough guide.
Frequently asked questions
What is the difference between takt time and cycle time?
Takt time is set by demand: available time divided by units ordered. Cycle time is measured on the process: how long a station actually takes per unit. For the line to keep up, every cycle time must be at or below takt.
Should breaks be included in takt time?
No. Subtract planned breaks, lunches and scheduled meetings from the shift before dividing. Unplanned stoppages are not subtracted; they show up as lost output against takt.
How do I calculate takt time for several shifts?
Use the total net time across the shifts and the total demand for the same period. Two 450-minute shifts against 900 units still give a 60-second takt.